How long does submittal review take?

Most construction contracts give the design team 10 to 21 calendar days per review cycle, and two weeks is the common middle. The real calendar time usually runs longer, because a submittal waits in a queue before anyone opens it, and every rejection starts a new cycle. The fastest reviews aren't fast reviewers. They're complete packages.

What the contract actually says

The review window lives in the specification, usually Section 01 33 00, Submittal Procedures. Typical language allows 10 to 14 calendar days for the architect's review, and around 21 days when a consultant or the owner reviews in sequence. The window starts when the architect receives the submittal, not when the sub sends it: the general contractor's routing time sits on top.

Why real reviews run past the window

Three things stretch the calendar. First, the queue: a reviewer carrying a full project load opens submittals in batches, so an item can sit days before its window effectively begins. Second, the package itself: an unindexed package with unmarked catalog pages takes multiples of the time a clean one takes, and is the likeliest to be returned unreviewed. Third, routing: sub to GC to architect to consultant and back is five handoffs, each with its own inbox.

How many hours a week does submittal review take?

The contract sets the calendar, but a reviewer's week is set by two numbers: how many packages arrive, and how long each one takes to read. Multiply them. Take a week with six packages in: at an hour each that's six hours of review, at two hours each it's twelve, and that's before any of them come back as resubmittals.

The second number is the one you can change. Most of the time in a review goes to searching: finding the schedule row, the spec article and the right line on a catalog page for each item, then putting them side by side. The decision itself is quick once everything is lined up. That's why the same reviewer can spend minutes on one package and an afternoon on the next. The difference is how much hunting the package leaves for them.

The resubmittal multiplier

Revise and resubmit doesn't add days to the current cycle; it starts a new one. The sub corrects and repackages, the GC re-routes, and the review window opens again, so one rejection commonly turns two weeks into five or six. On long-lead equipment the cycle sits directly on the procurement path, which is why switchgear and air handlers get expedited at real cost when a cycle repeats. Nobody wins a resubmittal, and most rejections come from the same handful of causes.

What one timed package showed

On our sample project we timed one plumbing package, 23 items, from upload to the architect's issued revision. Beem's read took 11 minutes, from upload to every item matched against the drawings and spec with its differences flagged. The architect's final pass on that prepared package took 61 minutes on the clock, from first action to the issued revision, and 13 of the 23 items went back to the contractor. We didn't time a pass on the raw package, so this isn't a before-and-after. It's one package, measured once.

What it does show is where the hour went: deciding, item by item, with the evidence already beside each one. Beem's own turnaround is 48 hours from a complete package. The reviewer's calendar stays the contract's.

Questions people ask

How many days does the architect have to review a submittal?

Whatever Section 01 33 00 of the project specification says: commonly 10 to 14 calendar days, and around 21 when consultants or the owner review in sequence. The window starts at the architect's receipt, after the general contractor's routing.

How many hours a week does submittal review take?

Packages received in the week times the reading time per package. Six packages at an hour each is six hours; at two hours each it's twelve. Reading time depends mostly on how much searching the package leaves: an indexed package with every model marked and the values set beside the schedule reads far faster than a catalog dump.

Why did my submittal take six weeks?

Usually a rejection. Revise and resubmit starts a whole new cycle: correction, repackaging, re-routing and a fresh review window, so one rejection commonly turns a two-week window into five or six weeks of calendar time.

Does resubmitting restart the review clock?

Yes. A resubmittal is a new submittal with a new review window. That is why the check before the package leaves, against the drawings and the spec, is worth more than any amount of pressure on the reviewer afterwards.